Production Metrics & Process Time Calculation
Production Metrics
- Takt Time (TT) = Net production Time (PT) / Units Customer Demand (UD)
- CycleTime (CT) = Net Production Time (PT) / Units Produced (UP)
- Lead Time (LT) = Time from order to dispatch
- Crew size (CS) = Cycle Time (CT) / Takt Time (TT)
- CT <= TT ===> enough resources. If CT > TT need more resources or improve process.
- Takt time is external – target: That is demand based.
- Cycle time is internal – actual: That is process based. Reduced only when process improves.